All glazed windows and doors are now in the extension, first fix electrics well under way and the underfloor heating has been started to put warm water through the system to help with drying out the building ready for plaster boarding...
... with all the rain though the land is saturated
Our project to restore and extend this timber framed cottage located on the edge of The Cotswolds near to Sudeley Castle in Winchcombe, Gloucestershire
Friday, 26 January 2018
Monday, 22 January 2018
Sunday, 14 January 2018
This will be the year...
... we complete and move to Lanes Cottage
After a break for Christmas and New Year the build progresses with more work on the roof and the glazed link being readied for the windows.
After a break for Christmas and New Year the build progresses with more work on the roof and the glazed link being readied for the windows.
Thursday, 21 December 2017
Chim Chim Cher-ee
... we have a chimney. Lots of work going on but not much to see includes underground sewers, sealing the roofs.
Work commenced 6 months ago today
Work commenced 6 months ago today
Sunday, 10 December 2017
Thursday, 30 November 2017
Saturday, 25 November 2017
Saturday, 18 November 2017
Friday, 17 November 2017
Going through changes...
Lots happening... remainder of the steel erected, floor fully screeded (covered now for protection), partition walls going up plus more....